Michigan building permits, inspections and occupancy: the basics

Written by

in

Michigan’s Stille-DeRossett-Hale Single State Construction Code Act (1972 PA 230) sets the ground rules for permits and inspections. The law calls the office that issues permits and inspects the work the “enforcing agency.”

The permit

  • Before construction, the owner or the owner’s builder, architect, engineer or agent applies in writing to the enforcing agency, with the fee, plans drawn to scale and a site plan (MCL 125.1510(1)).
  • If you apply as the owner’s builder, you file a written contract or letter of authorization from the owner. A residential builder or M&A contractor must list their license number and its expiration date (MCL 125.1510(2)).
  • The agency must grant or deny the application within 10 business days, or 15 for an unusually complicated building. If it doesn’t act in time, that counts as a denial you can appeal (MCL 125.1511(1)).
  • Except as the act or code allows, don’t start work until the permit is issued, and build to the approved plans (MCL 125.1511(1)).

Inspections

  • The enforcing agency inspects permitted work periodically (MCL 125.1512(1)).
  • Inspections happen between 8 a.m. and 6 p.m. on business days or while work is going on, except in an emergency or with permission (MCL 125.1512(2)).
  • If work doesn’t match the permit or the code, the agency sends written notice. If you don’t show good cause within 1 full working day, it posts a stop-construction order (MCL 125.1512(3)).

Certificate of occupancy

  • A new building can’t be used or occupied until a certificate of use and occupancy is issued (MCL 125.1513).
  • For alterations, an existing use that didn’t stop during the work can continue for 30 days after completion without a new certificate (MCL 125.1513).
  • Once the work qualifies, the agency issues the certificate within 5 business days of a written application and fee. A temporary certificate is possible for parts that are safe to occupy (MCL 125.1513).
  • The agency gives at least 12 hours’ notice of the final inspection (MCL 125.1513).

What to do

  • Carry your license number and expiration date to every permit application.
  • Don’t schedule move-in until the certificate of occupancy is issued.
  • Fees and local procedures vary, so check with your local building department.