Michigan Skilled Trades Regulation Act explained for electricians

Written by

in

The Skilled Trades Regulation Act is the state law behind every Michigan electrical license. It covers who has to be licensed, who can pull a permit, what the experience requirements are, and what happens if you work without a license. It’s a separate thing from the electrical code (the NEC as amended by Michigan) and from the skilled trades rules LARA is rewriting. This page explains how the act is put together and what it says to electricians, quoting the statute.

What the act is

  • It’s 2016 PA 407, MCL 339.5101 to 339.6133, and it’s cited as the “skilled trades regulation act.” It took effect April 4, 2017 (MCL 339.5101; Act 407 index).
  • It replaced the separate trade acts, including former 1956 PA 217 for electricians. Licenses issued under a former act carried over until they expire, and rules made under the former acts stay in effect where they don’t conflict with the new act (MCL 339.5109).
  • It has 11 articles. Articles 1–6 apply to every trade: definitions, issuing licenses, boards, fees, complaints and investigations, and penalties. Articles 7–11 cover the trades: Article 7 electricians and electrical contractors, Article 8 mechanical contractors, Article 9 boilers, Article 10 building officials and inspectors, and Article 11 plumbers (Act 407 index).

Act, code and rules: three different things

  • The act (PA 407) covers licensing and enforcement.
  • The licensing rules, R 339.5101–5412, are LARA’s Skilled Trades Regulation Rules, issued under sections 207, 209 and 907 of the act (R 339.5101–5412). A rewrite, 2025-58 LR, still shows Filing date: Pending as of Nov 19, 2026 (2025-58 LR tracker).
  • The electrical code, Part 8, is issued under a different law, the Stille-DeRossett-Hale single state construction code act, 1972 PA 230 (R 408.30801–30880). LARA lists the 2023 NEC as the current code, effective March 12, 2024 (LARA code books).

Article 7: who must be licensed

  • “Only an individual who is licensed under this article shall install electrical wiring.” Where inspection service is provided, a permit is required from the board or the municipality with jurisdiction (MCL 339.5731(1)).
  • No one may engage in the business of electrical contracting without an electrical contractor’s license from the board or the appropriate municipality. An individual may not execute electrical wiring unless they’re licensed under Article 7 and employed by, and working under the direction of, a licensed electrical contractor (MCL 339.5737(1)–(2)).
  • Fire alarm work and electric sign work each require a license too (MCL 339.5731(3)–(4)).

Work the act exempts

MCL 339.5737(3) lists classes of work that don’t need a license. A few that come up on jobs:

  • minor repair work
  • a homeowner’s own electrical work in the single-family home and outbuildings they own and live in, or will live in
  • work by licensed mechanical contractors in certain classifications and licensed plumbing contractors, and their employees, on control wiring and electrical parts of existing mechanical and plumbing systems on the load side of the unit disconnect, except life safety wiring
  • listed lawn irrigation and landscape lighting equipment, except permanent wired connections over 30 volts
  • security alarm systems
  • telecommunications work by companies primarily in that industry (fire alarm systems are not included in this exemption)

License levels in the act

  • Journeyman: at least 20 years old, with at least 8,000 hours of experience over at least 4 years under the direct supervision of a licensee (MCL 339.5715(1)).
  • Master: at least 22 years old, with at least 12,000 hours over 6 years or more under a master electrician’s supervision and a journeyman license held for at least 2 years (MCL 339.5713(1)).
  • Contractor: issued to a master electrician, or to a business with at least 1 full-time master electrician who lives in Michigan and is in charge of code compliance. A master can qualify only 1 contractor license (MCL 339.5711; MCL 339.5713(3)).
  • Exam retakes: fail the journeyman or master exam twice within 2 years and you wait at least 1 year. To sit again, you show you’ve completed a board-approved course on the Michigan electrical code, electrical fundamentals or electrical theory (MCL 339.5713(2); MCL 339.5715(3)).
  • Code update course: to renew, masters and journeymen must complete a board-approved course on any state construction code update within 12 months after the change (MCL 339.5713(4); MCL 339.5715(4)).

City licenses and registration

A municipality with its own licensing and inspection ordinance that meets the act’s standards can run its own program, and Article 7 doesn’t apply in its jurisdiction. State licenses, and municipal licenses issued under standards at least as strict, “shall be recognized by all municipalities.” Cities that provide electrical inspection can require contractors to register, but licensed journeymen don’t have to register to work in places under the board’s jurisdiction (MCL 339.5733; MCL 339.5735).

Penalties for unlicensed work

Practicing a regulated trade without a license, including on a suspended, revoked or lapsed license, is a misdemeanor: up to $500 and/or 90 days the first time, and up to $1,000 and/or 1 year the second time. A third or later offense is a felony, with up to $25,000 and/or 5 years. Courts can order restitution, and affected people, including licensees, can sue for an injunction (MCL 339.5601).

What to do

  • Know which article covers you (Article 7), and keep the act, the Part 8 code rules and the R 339 licensing rules separate in your head.
  • Before you hire or sub out, confirm the license level matches the work. Use the act’s exemption list before you assume a job doesn’t need a license.
  • Watch the 2025-58 LR tracker. The act stays the same, but the rules under it are changing.

Sources: 2016 PA 407 (MCL 339.5101–339.6133) · MCL 339.5737 · MCL 339.5601 · R 339.5101–5412 · 2025-58 LR tracker · LARA code books

More for Electrical contractors: Michigan Electrical updates.

Want a free sample issue? Sign up for the free sample. Pick your trades and we’ll email you the sample PDF.

Michigan Code Brief · Not legal advice. Every fact links to its official source. Checked Nov 19, 2026. Confirm with LARA or your local building department before you act.