Category: HVAC/Mechanical

  • Boiler licenses renew by December 31

    If you or a tech carry a Michigan boiler license, it renews every year by December 31. Renewal opens 90 days early, so you can do it now.

    Who this hits

    LARA’s Bureau of Construction Codes lists four boiler license types:
    – Boiler Installer: $100. Late fee $100 after 60 days. If expired more than 3 years, you re-apply and re-test.
    – Boiler Repairer: $100. Late fee $100 after 60 days. If expired more than 3 years, you re-apply and re-test.
    – Boiler Inspector: $100, or $80 for low/high pressure license holders. Late fee to match after 60 days.
    – Boiler Operator: $100 for stationary engineer, $80 for low/high pressure. Late fee to match after 60 days.

    None of these need a code-update course to renew.

    A typical small-shop scenario

    You do mostly furnaces and AC. One senior tech holds a boiler installer license for the hydronic jobs every winter. If that renewal slips past Dec 31, they’re working on an expired license right when boiler season peaks. Wait past the 60-day grace window and you also eat a $100 late fee. Let it go 3 years and they’re back at the exam.

    How to renew

    • Express Pay works without logging in.
    • Or log into Accela, LARA’s online system. Update your address first if it changed. You may need to link the license to your account before you can renew.

    What to do this month

    • List everyone in the shop with a boiler license and their expiration date.
    • Renew in November, before the holiday rush.
    • Put Dec 31 on next year’s calendar too. It’s annual.

    Also coming: Michigan is rewriting the Boiler Code rules. See the rulemaking roundup.

    Source: LARA BCC license renewals

    More for HVAC/Mechanical contractors: Michigan HVAC/Mechanical updates.

    Michigan Code Brief · Not legal advice. Every fact links to its official source. Checked Oct 15, 2026. Confirm with LARA or your local building department before you act.

  • Michigan Mechanical Code is moving to the 2024 IMC

    Michigan’s mechanical code is based on the International Mechanical Code (IMC). Right now it’s the 2021 IMC, which took effect March 12, 2024. LARA has proposed moving to the 2024 IMC.

    Where it stands

    • Rule set: Construction Code, Part 9A Mechanical Code (LARA lists it as 2025-7 LR).
    • The proposed rules were published in the July 15, 2026 Michigan Register.
    • The public hearing was August 5, 2026 in Lansing. Written comments closed August 7, 2026.
    • It takes effect 120 days after LARA files it with the Secretary of State.

    Status: As of Oct 15, 2026, the state has not filed these rules or published an effective date. The final rule text went to the Legislature’s Joint Committee on Administrative Rules on Oct 12, 2026 (state rule tracker, 2025-7 LR). Until it’s filed, and for 120 days after, the 2021 IMC still governs.

    Who it affects

    Anyone who pulls mechanical permits in Michigan: residential HVAC, light commercial, hydronics, ductwork. It matters most on jobs permitted around the switchover. Which code applies usually depends on when the permit is applied for. Ask your local building department which edition they’ll apply to permits filed around the switchover.

    What actually changes

    LARA says the rules adopt the 2024 IMC “with amendments, deletions, and additions” for Michigan. They haven’t published a plain summary. The final rule text is posted on the state rule tracker (“Final Rule Language”). We’ll break down the section changes once it’s filed.

    What to do

    • Now: Get on the list. Email LARA-BCC-Rules@michigan.gov with the subject “Subscribe – MECHANICAL”. It’s free.
    • When it’s filed: You’ll have about 4 months. Buy or access the 2024 IMC, read the Michigan amendments, and brief your installers.
    • Michigan mechanical contractors don’t need a code-update course for their license, per LARA. The training is on you.

    Example

    You quote a light-commercial rooftop replacement in January for a spring install. If the 2024 IMC takes effect in between, ask the local inspector which edition they’ll hold you to. Get the answer in writing.

    Source: LARA BCC currently open rules · LARA license renewals (no code-update requirement)

    More for HVAC/Mechanical contractors: Michigan HVAC/Mechanical updates.

    Michigan Code Brief · Not legal advice. Every fact links to its official source. Checked Oct 15, 2026. Confirm with LARA or your local building department before you act.

  • EPA’s 15 lb HFC leak rule: what it means for a small Michigan shop

    Short version: there’s a federal leak repair rule for HFC systems, and it’s been live since January 1, 2026. Most of your residential changeouts aren’t covered. Your commercial refrigeration customers probably are.

    What the rule is

    It’s part of EPA’s Emissions Reduction and Reclamation rule, written under the AIM Act. The citation is 40 CFR Part 84, Subpart C, and the leak section is 84.106. It covers appliances with a full charge of 15 pounds or more of an HFC refrigerant, or of a substitute with a GWP above 53.

    Don’t mix it up with the older Section 608 rule. That one uses a 50 lb threshold and covers ozone-depleting refrigerants like R-22. It still exists. This is a second, separate rule aimed at HFCs.

    What’s NOT covered

    This matters most for a shop like ours. EPA’s fact sheet says appliances in the residential and light commercial air conditioning and heat pump subsector are not covered by these leak repair requirements. Your typical 3-ton split system in a Benton Harbor ranch house isn’t in scope. Neither are systems running refrigerants with a GWP of 53 or below.

    What IS covered

    Think walk-in coolers and freezers, reach-in rack systems, supermarket systems, process chillers, and larger commercial comfort-cooling equipment. Anything 15 lb or more on an HFC like R-404A, R-134a or R-410A, outside the residential/light-commercial AC subsector.

    How it works on a service call

    1. Every time you add refrigerant to a covered appliance, the owner has to calculate a leak rate. The rule names a few exceptions: right after a retrofit, a new install, or a seasonal variance.
    2. If the leak rate is over the threshold, the clock starts. The thresholds are 30% for industrial process refrigeration, 20% for commercial refrigeration, and 10% for everything else.
    3. The leak has to be found and repaired within 30 days, or 120 days if an industrial process shutdown is needed.
    4. Verification tests confirm the fix.

    Example: you top off a restaurant’s walk-in. It holds 22 lb of R-404A. You add 6 lb. Annualized, that’s well over 20%. The owner now has 30 days to get it fixed. Your job is to tell them, document it, and quote the repair.

    Paperwork

    Whoever adds or removes refrigerant has to give the owner documentation. That covers the appliance and its location, the date, the parts worked on, the type of service, the tech’s name, and the refrigerant type and amount. The owner keeps these records for at least three years. Full-charge records are kept until three years after the unit is retired. Owners also had to determine the full charge of every covered appliance by Jan 1, 2026, or at installation for newer units.

    Reports go to EPA in some cases: extension requests, retrofit or retirement plans, and chronic leakers (more than 125% of full charge lost in a calendar year).

    What to do this month

    • Sort your commercial customers into “15 lb+ HFC” and “not covered.”
    • Add charge size, refrigerant added and leak rate fields to your service ticket.
    • Explain the 30-day clock to the owners. Most have never heard of it.

    Still moving

    In May 2026 EPA proposed exempting road and shipping-container transport refrigeration units. That doesn’t touch typical HVAC work. We found no proposal to change the 15 lb threshold itself.

    Sources: EPA leak repair fact sheet · 40 CFR 84.106 · EPA reporting resources

    More for HVAC/Mechanical contractors: Michigan HVAC/Mechanical updates.

    Michigan Code Brief · Not legal advice. Every fact links to its official source. Checked Oct 15, 2026. Confirm with LARA or your local building department before you act.