For two years we heard “you can’t install R-410A after January 1, 2026.” That’s no longer true. EPA removed the deadline.
What happened
- EPA’s 2023 Technology Transitions rule set a GWP limit of 700 for new residential and light-commercial AC and heat pump systems. R-410A is well above 700. R-454B and R-32 are under it.
- New systems like that couldn’t be made or imported after January 1, 2025.
- A December 2023 interim rule let contractors install leftover inventory through December 31, 2025, if every component was made or imported before Jan 1, 2025.
- In 2026 EPA finalized a reconsideration rule (published in the Federal Register May 26, 2026, 91 FR 31284). It took effect July 27, 2026 and removed the installation deadline for those qualifying systems.
What it means for you
- You can install an R-410A split system, mini-split or packaged unit for residential or light commercial with no federal end date, as long as every specified component was manufactured or imported before January 1, 2025.
- New R-410A systems still can’t be manufactured or imported. Supply only shrinks from here.
- Servicing existing R-410A systems is still allowed. EPA kept the ability to use replacement components labeled “for servicing existing equipment only.”
Practical example
A customer’s 2012 R-410A heat pump dies. They want the cheapest replacement. Your distributor has a matched R-410A condenser and coil. Check the manufacture date on both. Both pre-2025? Federally, you’re fine. One made after Jan 1, 2025? Don’t install that combo. Keep a photo of the data plates in the job file.
Don’t over-read it
This is the federal rule. Michigan’s construction code applies statewide (MCL 125.1508a), and the current Michigan Mechanical Code rules don’t mention R-410A or HFC phase-down dates (Part 9A rules). For A2L refrigerants (R-454B, R-32), the Michigan Mechanical Code says A2L systems “shall comply with ASHRAE 15” (R 408.30947b). Follow the manufacturer’s instructions too.
What to do
- Ask your distributor for date codes before you quote R-410A.
- Keep training techs on A2L equipment. That’s where new product is going.
Sources: Federal Register, 91 FR 31284 · EPA restrictions by sector · ABC summary
Related
- VRF systems: January 1, 2027 install cutoff
- A2L refrigerants: the basics for R-454B and R-32 work
- EPA’s 15 lb HFC leak rule: what it means for a small Michigan shop
More for HVAC/Mechanical contractors: Michigan HVAC/Mechanical updates.
Michigan Code Brief · Not legal advice. Every fact links to its official source. Checked Oct 15, 2026. Confirm with LARA or your local building department before you act.