Category: HVAC/Mechanical

  • Michigan mechanical code ventilation and exhaust: what Michigan changes

    For ventilation on commercial and multifamily work, Michigan uses the 2021 International Mechanical Code (IMC) Chapter 4 as published. Michigan doesn’t rewrite any of it. Where Michigan does change things is on the exhaust side: where exhaust and dryer ducts can terminate, how dryer ducts are supported, and how kitchen hoods are tested. Houses follow the Michigan Residential Code, which has its own exhaust amendments. A pending 2024 IMC rule set would drop the commercial exhaust amendments. Here’s what is in force as of Nov 19, 2026 and what’s pending.

    Which code covers ventilation

    • The Michigan Mechanical Code is the 2021 IMC, adopted by reference except for a short list of sections (R 408.30901a). None of the excluded sections are in Chapter 4 (Ventilation), and none of Michigan’s Part 9A amendment rules change a Chapter 4 section, so the 2021 IMC ventilation text applies as written (R 408.30901–408.30998).
    • LARA lists the 2021 Michigan Mechanical Code as current, effective March 12, 2024, and notes that “Residential requirements are contained in the Michigan Residential Code” (LARA code books).
    • Michigan adds a definition of “occupiable space” to the code: a room or enclosed space designed for human occupancy where people gather or work, “equipped with means of egress, heat, light, and ventilation facilities.” It doesn’t include spaces meant mainly for other uses, such as storage rooms and equipment rooms (R 408.30905a).

    Michigan exhaust amendments (commercial, in force)

    Michigan rewrites IMC sections 501.3, 504.4 and 504.9.2 (R 408.30945a):

    • Exhaust discharge (501.3): exhaust air must go outdoors where it won’t cause a public nuisance and can’t readily be drawn back in by a ventilating system. “Air shall not be exhausted into an attic or a crawl space, be directed onto walkways, or terminate within 3 feet of a ventilated section in a soffit.” Exceptions: whole-house attic fans in dwelling units with private attics, commercial cooking recirculating systems, and listed and labeled domestic ductless range hoods installed per the manufacturer’s instructions where Chapter 4 ventilation is otherwise provided.
    • Dryer exhaust termination (504.4): terminate outside the building, not within 3 feet of a ventilated soffit section, with a back-draft damper and no screen. Don’t use sheet metal screws or other fasteners that block the airflow, and don’t connect the duct to a vent connector, vent or chimney.
    • Dryer duct support (504.9.2): support and secure dryer exhaust ducts every 4 feet, install the insert end in the direction of airflow, and use no screws or fasteners that stick into the duct.

    Kitchen hoods: Michigan’s capture and containment test

    Michigan adds section 507.6.1.1. The field capture and containment test in 507.6.1 must follow the Bureau of Construction Codes’ smoke testing procedures, which are free from the bureau (R 408.30935a).

    Permits

    Michigan’s permit exemption list includes “portable ventilation appliances and equipment.” Fixed ventilation and exhaust systems aren’t on that list (R 408.30906a, section 106.2(b)).

    Houses: Michigan Residential Code exhaust rules

    One- and two-family homes fall under the 2015 Michigan Residential Code, which is still in effect under the court stay on the 2021 update (LARA Currently Open Rules). Its Michigan amendments (R 408.30500–408.30547g):

    • Exhaust openings (R303.5.2, R 408.30544): not directed onto walkways, not within 3 feet of a ventilated soffit section, and located so they don’t create a nuisance.
    • Dryer duct termination (M1502.3, R 408.30507): outside the building and per the dryer manufacturer’s instructions. If the instructions don’t say where, at least 3 feet in any direction from openings into buildings or a ventilated soffit section. A backdraft damper is required and a screen isn’t allowed.
    • Dryer duct support (M1502.4.2, R 408.30541a): supported at 4-foot intervals, insert end in the direction of airflow, and no screws that stick into the duct.

    Pending: the 2024 IMC rule set

    The 2025-7 LR tracker still shows Filing date: Pending and Effective date: Pending as of Nov 19, 2026. The rules take effect 120 days after filing. The final rule language would:

    • adopt the 2024 IMC, with appendices A, D and E as permissive guidelines only
    • rescind R 408.30945a, the Michigan exhaust and dryer amendments above, along with R 408.30947b
    • keep the “occupiable space” definition
    • amend 1109.3.2: refrigerant pipe shafts with A2L or B2L systems must be naturally or mechanically ventilated, and shafts with any A2, A3, B2 or B3 system must be continuously mechanically ventilated with a refrigerant detector. Detector-activated ventilation must start at no more than 25% of the refrigerant’s lower flammable limit.

    None of this is in force until the tracker shows a filing date. Until then, follow the 2021 rules above.

    What to do

    • For commercial ventilation rates and Chapter 4 requirements, work from the 2021 IMC text. Michigan doesn’t change it.
    • Keep exhaust and dryer terminations at least 3 feet from ventilated soffits, out of attics and crawl spaces, and off walkways. Support dryer ducts every 4 feet.
    • Get the BCC smoke test procedure before a commercial hood test.
    • Watch the 2025-7 LR tracker for a filing date.

    Sources: R 408.30901–408.30998 · R 408.30500–408.30547g · LARA code books · LARA Currently Open Rules · 2025-7 LR tracker

    More for HVAC/Mechanical contractors: Michigan HVAC/Mechanical updates.

    Want a free sample issue? Sign up for the free sample. Pick your trades and we’ll email you the sample PDF.

    Michigan Code Brief · Not legal advice. Every fact links to its official source. Checked Nov 19, 2026. Confirm with LARA or your local building department before you act.

  • Michigan boiler license requirements: installer and repairer classes

    If you install or alter boilers in Michigan (outside the residential carve-outs), you need a boiler license and a state boiler permit before the work starts. This page covers how to get licensed — not how to renew. Renewals are every Dec 31; see the related renewal post below.

    Why it matters

    • LARA’s boiler permit page states that installation and repairs of boilers and high-pressure piping may be done only by persons licensed by the Boiler Section, and that permits will not be issued to unlicensed persons (LARA boiler permit information).
    • Under the Skilled Trades Regulation Act, a person shall not install or alter a boiler without first obtaining a permit from the boiler division. You are not eligible for that permit if you are not licensed under the boiler article, and unlicensed individuals may perform permit work only under the immediate supervision of a licensee (MCL 339.5939).
    • The boiler article does not apply to certain boilers, including steam or vapor boilers at not more than 15 psig in a private residence or in an apartment of fewer than six families, and hot-water boilers at not more than 160 psig or 250°F in those same locations, plus other listed exemptions such as agricultural and federal-control boilers (MCL 339.5915). If the boiler is outside that list, plan on licensing and permits.

    Installer and repairer experience (rules in force)

    Current skilled-trades rules require a boiler installer or repairer license as required by MCL 339.5939 (R 339.5173):

    • Installer: at least 5 years of experience in all phases of boiler installation in the class you are applying for. Up to 2 years credit may be given for 2 years of experience in the design, construction, manufacture or inspection of boilers.
    • Repairer: at least 5 years of experience in all phases of boiler repair in that class. Up to 3 years credit may be given for 3 years of design, construction, manufacture or inspection experience.

    LARA’s pathway page adds: submit an application and fee, get approved to test, then pass the exam; hold your current boiler license at least one year before upgrading classifications (LARA pathway to licensure). Written license exams require a score of 75% (R 339.5114). PSI administers installer/repairer exams after LARA approval; pay exam fees to PSI when you schedule (LARA boiler licensing page).

    Installer classes

    Class scope is in R 339.5174 and restated on LARA’s boiler licensing page:

    • 1B: low-pressure boiler not exceeding 1,000,000 BTU/hour firing rate (modular sum also capped at that rate)
    • 2B: low-pressure boiler of any capacity or firing rate, plus 1B work
    • 3B: power boiler ≤ 5,000 lb steam/hour; install/replace non-boiler external piping (ASME B31.1 / R 339.5209); plus 2B work
    • 4B: power boiler ≤ 300,000 lb steam/hour; non-boiler external piping; plus 3B work
    • 5B: power boiler of any capacity except nuclear heat source; non-boiler external piping; plus 4B work
    • 6B: nuclear heat-source boiler (extra federal/ASME evidence required)
    • P: install or replace (and, for repairer P, repair) non-boiler external piping only

    Repairer classes

    From R 339.5175:

    • I: repair a low-pressure boiler by means other than welding, riveting or other fabrication
    • II: repair low-pressure, hot-water supply and fire-tube boilers of any pressure; plus Class I
    • III: repair high-pressure boilers; repair or replace non-boiler external piping; plus Class II
    • IV: repair or field-erect a boiler of any pressure except nuclear heat source; non-boiler external piping
    • V: erect and repair nuclear heat-source boilers (ASME N-type stamp evidence required)
    • P: non-boiler external piping only

    Match the class to the boiler you will actually work on before you apply.

    Fees (current rules)

    R 339.5176 sets installer and repairer license, examination and renewal fees at $100 each. Permit application fees in the same rule include $100 for a low-pressure installation permit and $130 plus $0.06 per foot of piping for a high-pressure installation permit, among others. Apply online through Accela when you can (LARA boiler permits; aca-prod.accela.com/LARA).

    Pending rules (not in force)

    Two related rule sets still show Filing date: Pending and Effective date: Pending as of Nov 5, 2026:

    • Boiler Code rewrite — 2025-64 LR tracker (final rules + JCAR package posted; takes effect 90 days after filing once filed)
    • Skilled Trades Regulation Rules rewrite — 2025-58 LR tracker (same status). Its final R 339.5173 text would require “not less than 5 years and 10,000 hours” of experience with notarized employer statements. That hour figure is not in the Admin Code in force today; treat it as pending until the tracker shows a filing date.

    What to do

    • Confirm whether MCL 339.5915 takes the boiler out of the article. If not, pick the installer or repairer class that matches the equipment.
    • Document your five years in that class, apply through LARA/Accela, then schedule PSI.
    • Do not start install or alteration work until the boiler division issues the permit (MCL 339.5939).

    Sources: MCL 339.5915 · MCL 339.5939 · R 339.5101–5412 · LARA boiler licensing · LARA boiler permits · 2025-64 LR · 2025-58 LR

    Want a free sample issue? Sign up for the free sample. Pick your trades and we’ll email you the sample PDF.

    More for HVAC/Mechanical contractors: Michigan HVAC/Mechanical updates.

    Michigan Code Brief · Not legal advice. Every fact links to its official source. Checked Nov 5, 2026. Confirm with LARA or your local building department before you act.

  • Michigan mechanical contractor license: classifications and requirements

    Michigan licenses mechanical work by classification. One mechanical contractor license can carry several. The list and the experience rules are in the Skilled Trades Regulation Act, not in a local city ordinance.

    Who needs a mechanical contractor license

    Under MCL 339.5809, you generally need a mechanical contractor’s license (with the right classification) and the appropriate permit before you install, alter or service work in the classifications below. LARA’s mechanical page says licensed mechanical contractors can perform installations, alterations and servicing, and secure permits.

    A municipality can’t invent its own mechanical licensing requirements for those classifications (MCL 339.5811).

    The work classifications

    MCL 339.5807(2) lists these classifications. LARA’s mechanical licensing page lists the same ones:

    1. Hydronic heating and cooling and process piping
    2. HVAC equipment
    3. Ductwork
    4. Refrigeration
    5. Limited heating service
    6. Limited refrigeration and air conditioning service
    7. Unlimited heating service
    8. Unlimited refrigeration and air conditioning service
    9. Fire suppression
    10. Specialty

    “Limited” and “unlimited” service, and what “specialty” covers (solar heating and cooling; solid fuel and vented decorative gas appliances; LP distribution piping; fuel gas piping; fuel gas piping and venting), are defined in MCL 339.5803 and in R 339.5161. If you already hold the HVAC equipment classification, R 339.5161(2) says you don’t also need those specialty licenses for that specialty work.

    Experience and exams

    • For a new classification, you generally need 3 years or 6,000 hours of experience in that classification, shown with employer statements signed under penalty of perjury (MCL 339.5807(1)(a)). LARA restates the same rule on its mechanical licensing page.
    • A completed 2-year (or equivalent) HVAC program from a recognized school, or a USDOL-approved 2-year HVAC training program, can count for up to 1 year / 2,000 hours of that experience (MCL 339.5807(5)).
    • Military experience can count with the right discharge papers and a commanding-officer affidavit (MCL 339.5807(3)–(4)).
    • Adding a classification to an existing license: LARA’s experience-requirements notice says you must have held the prerequisite classification for at least 3 years immediately before you apply (for example, ductwork requires HVAC equipment). The statute sets out the same prerequisite pairs as a route to eligibility (MCL 339.5807(1)(b)).
    • You must take and pass an exam for each classification you want. PSI runs the exams; approved applicants schedule with PSI and pay the exam fee to PSI (LARA mechanical page).

    Fees and renewal

    • LARA’s experience notice: initial mechanical contractor license/classification application fee $300 (non-refundable). Adding a classification mid-cycle: $300 / $200 / $100 depending on year of the license cycle.
    • Renewal: every three years by August 31. Not every contractor renews in the same year. Renewal fee $300; late fee $100 if you miss the deadline (LARA renewals). You can start renewing 90 days before expiration.
    • If the license has been expired more than 3 years, LARA says you re-apply and re-test.
    • LARA’s renewals page says you are not required to take code-update courses for a mechanical contractor license under the rules in force today.

    Coming up: pending Skilled Trades rules

    The Skilled Trades Regulation Rules rewrite (2025-58 LR) has final rule language and a JCAR report posted Sept 29, 2026. As of Oct 19, 2026, its Filing date and Effective date are Pending, and the final rules say they take effect 90 days after filing (state rule tracker, 2025-58 LR). The final language of R 339.5161 would add three things for mechanical contractors. These are not in effect yet:

    • Code-update course at renewal: “As a condition of renewal of a mechanical contractor license, a mechanical contractor shall demonstrate the successful completion of a course, approved by the department, concerning any update or change in the Stille-DeRossett-Hale single state construction code act, 1972 PA 230, MCL 125.1501 to 125.1531, within 12 months after the update or change in that code.” It applies only in or after years the code changes.
    • Boiler route to hydronic: holding at least a low-pressure boiler installer license for at least 1 year could stand in for experience for classification 1, hydronic heating and cooling and process piping.
    • Adding a classification: submit the department’s application with the non-refundable application fee.

    Michigan is also moving to the 2024 IMC (rule set 2025-7 LR, filing Pending). If both take effect, the code-update course rule would matter for that change. See our 2024 IMC post below.

    What to do

    • Confirm which classifications your company actually holds before you bid a fire-suppression, hydronic or unlimited-service job.
    • Apply and renew through Accela: aca-prod.accela.com/LARA.
    • Use LARA’s mechanical contractor application and keep the employer statements detailed (BTU ratings, refrigerants, equipment types, dates).

    Sources: MCL 339.5807 · MCL 339.5809 · MCL 339.5803 · LARA mechanical licensing · LARA renewals · R 339.5101–5412

    Want a free sample issue? Sign up for the free sample. Pick your trades and we’ll email you the sample PDF.

    More for HVAC/Mechanical contractors: Michigan HVAC/Mechanical updates.

    Michigan Code Brief · Not legal advice. Every fact links to its official source. Checked Oct 19, 2026. Confirm with LARA or your local building department before you act.

  • 2026 NEC outdoor GFCI and your HVAC condensers

    This one lives in the electrical code, but it hits HVAC shops: nuisance-tripping condensers and heat pumps.

    What the 2026 NEC says (per NFPA)

    • 210.8(F): outdoor outlets at dwellings rated 60 A or less need GFCI protection.
    • The old Exception No. 2 for listed HVAC equipment expired Sept 1, 2026.
    • New Exception No. 3 allows a listed Class C special purpose GFCI (SPGFCI), listed to UL 943C, to protect listed HVAC equipment.
    • Industry coverage (EC&M) says that when Class C SPGFCI is used, the HVAC disconnect must be marked “Warning: Class C SPGFCI Protection Provided for HVAC Unit.” This comes from trade press. NFPA’s code text isn’t free to quote, so read 210.8(F) in the 2026 NEC before you rely on the exact label wording.

    Does this apply in Michigan yet?

    Not automatically.
    – Michigan’s electrical code is still the 2023 NEC. The 2026 NEC adoption is a draft.
    – One- and two-family homes fall under the Michigan Residential Code, which is on hold in court at its 2015-based version.
    – Michigan’s Aug 19, 2026 draft doesn’t amend 210.8(F) (draft rules, strike-bold). The draft can still change.

    So for now this is a heads-up, not a Michigan requirement on houses. Ask your inspector.

    Why HVAC should care anyway

    • Inverter heat pumps and condensers have historically had trouble with standard GFCIs. That’s why the exception existed.
    • When Michigan adopts the 2026 NEC, whoever wires your condenser may need GFCI or Class C SPGFCI protection, depending on Michigan’s amendments and the house-versus-commercial split.
    • If an electrician installs it, coordinate on equipment listing and what gets marked at the disconnect.

    Example

    A light-commercial client wants a new rooftop or ground-mount unit next year. Ask your electrician now whether the job will be inspected under the 2023 or 2026 NEC. Then you’re not surprised by a protection requirement at final.

    Sources: NFPA: Key Changes in the 2026 NEC · EC&M · LARA code books

    More for HVAC/Mechanical contractors: Michigan HVAC/Mechanical updates.

    Michigan Code Brief · Not legal advice. Every fact links to its official source. Checked Oct 15, 2026. Confirm with LARA or your local building department before you act.

  • Michigan mechanical permits: the basics

    The ground rules, straight from LARA and state law.

    Who needs a license

    A mechanical contractor’s license with the right classification is required to install, alter or service:
    1. Hydronic heating and cooling and process piping
    2. HVAC equipment
    3. Ductwork
    4. Refrigeration
    5. Limited heating service
    6. Unlimited heating service
    7. Limited refrigeration and AC service
    8. Unlimited refrigeration and AC service
    9. Fire suppression
    10. Specialty

    Exception: an owner of a single-family dwelling they occupy, or will occupy, can do the work without a license.

    When you need a permit

    LARA: “Except for replacement of minor parts, mechanical work shall not be started until a permit for such work has been issued.”
    – You pull the permit on work you do for an owner.
    – A homeowner doing their own work pulls their own.

    The homeowner rule (MCL 339.5819)

    An owner-occupant may install their own heating or refrigerating system if, on the permit application, they affirm they own and occupy the house, or will on completion, and will do the install. They also have to get the inspection after it’s running.

    Low-pressure boilers

    Permits for steam or vapor boilers at 15 psig or less in private residences, or apartment buildings under 6 families, must be secured by a licensed mechanical contractor with the hydronic heating and cooling and process piping classification.

    Where to apply

    • Check LARA’s Statewide Jurisdiction List first. Enforcement may be by the state, the county, or the city or township.
    • Apply online at aca-prod.accela.com/lara where the state enforces, or by mail (slower).
    • Questions: bccpermits@michigan.gov.

    Example

    A Berrien County furnace and AC changeout. Check the jurisdiction list to see who enforces mechanical there. Pull the permit before you start, and book the final inspection. “Replacement of minor parts” means things like a capacitor or igniter, not a new furnace.

    Sources: LARA mechanical permit information · MCL 339.5819

    More for HVAC/Mechanical contractors: Michigan HVAC/Mechanical updates.

    Michigan Code Brief · Not legal advice. Every fact links to its official source. Checked Oct 15, 2026. Confirm with LARA or your local building department before you act.

  • A2L refrigerants: the basics for R-454B and R-32 work

    New residential and light-commercial equipment has moved to A2L refrigerants, mainly R-454B and R-32. Here’s what EPA says, and where its guidance stops.

    What “A2L” means

    It’s an ASHRAE Standard 34 safety class. The “A” means lower toxicity. “2L” means lower flammability: it can burn, but less readily than an A2 or A3 like propane. EPA’s refrigerant safety page uses the ASHRAE 34 classes.

    EPA’s rules (SNAP)

    • SNAP Rule 23 listed R-452B, R-454A, R-454B, R-454C and R-457A as acceptable, subject to use conditions, for new residential and light-commercial AC and heat pumps. R-32 is listed the same way for that equipment, other than self-contained room ACs.
    • EPA says A2L listings in Rules 23 and 25 require compliance with UL 60335-2-40 Edition 3. Edition 4 equipment is OK to the extent it also meets Edition 3.
    • Charge size: to comply, you must use charge sizes that meet Edition 3, even where Edition 4 allows something different.
    • Labels: both the red GHS flame diamond and the yellow ISO 7010-W021 triangle are consistent with EPA rules.
    • EPA says following ASHRAE Standard 15 “will ensure the safety of technicians and building occupants.”

    Practical habits (general safety, per EPA)

    • Find and fix leaks promptly. Use leak detectors to warn of rising concentrations.
    • Keep exposures low, and check the SDS for each refrigerant.
    • Respect flammability limits. Control ignition sources where refrigerant could collect.
    • Install per the manufacturer’s instructions. A2L equipment often has sensors and mitigation built in.

    Michigan’s A2L rule

    Michigan already allows A2L systems. The current Michigan Mechanical Code, in effect since March 12, 2024, says “System using A2L refrigerants shall comply with ASHRAE 15” and adopts the 2022 edition of ASHRAE 15 (Mich. Admin. Code R 408.30947b and R 408.30901). Houses fall under the Michigan Residential Code, so ask your inspector how they apply it there.

    Not covered here

    • Specific tool and recovery-equipment rules for A2Ls.
    • Training or certification beyond EPA 608.

    Check the manufacturer, your distributor’s training and your inspector on these.

    Example

    You’re quoting your first R-454B heat pump in a small basement mechanical room. Read the installation manual’s minimum room area and charge section before you quote. If the unit needs a mitigation board or sensor, that’s part of the job.

    Sources: EPA SNAP Q&A · EPA SNAP Rule 23 fact sheet · EPA refrigerant safety · EPA restrictions by sector

    More for HVAC/Mechanical contractors: Michigan HVAC/Mechanical updates.

    Michigan Code Brief · Not legal advice. Every fact links to its official source. Checked Oct 15, 2026. Confirm with LARA or your local building department before you act.

  • Michigan Residential Code: still stuck in court

    Michigan tried to update its residential code and residential energy code. A court put that on hold. Here’s what applies today.

    What happened

    • LARA finished two rule sets that would adopt parts of the 2021 International Residential Code (IRC) and the 2021 IECC residential standards. They were set to take effect August 29, 2025.
    • On July 7, 2025, the Michigan Court of Claims issued an order in Home Builders Assoc. et al. v. LARA et al. It temporarily stops LARA from “taking additional steps necessary to apply or implement” those two rule sets while the case is pending.
    • While the order stands, the 2015 IRC and IECC residential provisions, as Michigan adopted them, remain in effect.

    As of Oct 15, 2026, LARA’s open rules page still says the 2015 versions “will remain valid and in effect” while the order stands.

    Why an HVAC shop cares

    The residential code covers a lot of house mechanical work: equipment sizing references, duct sealing and insulation, and energy provisions that affect what inspectors check on new homes and additions. For now, keep working to the 2015-based Michigan residential rules on houses.

    The mechanical code is separate (see our IMC explainer). It covers commercial and some residential work and is on its own update track.

    Example

    A builder calls you for a new-construction ranch in Berrien County. They mention “the new 2021 energy code.” Politely correct them. The 2021 residential update is on hold. Design and inspect to the current rules, and confirm with the local inspector.

    What to do

    • Don’t retrain your crew to the 2021 IRC/IECC yet.
    • Watch for the court outcome. If the order lifts, the update could move quickly.

    Source: LARA BCC currently open rules (court order details)

    More for HVAC/Mechanical contractors: Michigan HVAC/Mechanical updates.

    Michigan Code Brief · Not legal advice. Every fact links to its official source. Checked Oct 15, 2026. Confirm with LARA or your local building department before you act.

  • VRF systems: January 1, 2027 install cutoff

    Variable refrigerant flow (VRF) systems run on a different schedule from regular splits. If you do any VRF work, this is the date to watch.

    The rule

    Under EPA’s Technology Transitions rule (40 CFR 84.54), new residential and light-commercial VRF systems using refrigerants with a GWP of 700 or higher (R-410A is one) are restricted starting January 1, 2026 for manufacture and import.

    The install allowance:
    – High-GWP VRF systems can be installed until January 1, 2027, if all components were manufactured or imported before January 1, 2026.
    – Longer allowance, until January 1, 2028, if the building had an approved building permit issued before October 5, 2023 that specified the HFC system, and all components were made or imported before Jan 1, 2026.

    The R-410A deadline removal in July 2026 covered non-VRF residential and light-commercial systems. EPA’s table still shows the Jan 1, 2027 VRF date.

    Who this affects

    Mostly commercial and multifamily work: small offices, churches, mixed-use buildings. A small residential shop may never touch it. But if you sub on VRF jobs, or quoted one this year, this is your deadline.

    Example

    You quoted a 6-zone R-410A VRF system for a dental office, install planned for February 2027. That’s past the cutoff unless the building permit predates Oct 5, 2023 and specified it. Talk to the owner now. Pull the install into December, or switch to a lower-GWP system.

    What to do

    • List every open VRF quote and its refrigerant.
    • Confirm component manufacture dates with your distributor.
    • Anything landing after Dec 31, 2026: re-spec it or check the permit-date exception.

    Sources: EPA restrictions by sector · 40 CFR 84.54 (eCFR)

    More for HVAC/Mechanical contractors: Michigan HVAC/Mechanical updates.

    Michigan Code Brief · Not legal advice. Every fact links to its official source. Checked Oct 15, 2026. Confirm with LARA or your local building department before you act.

  • Michigan rulemaking roundup: Boiler Code and Skilled Trades rules

    Two Michigan rule sets in the works could touch an HVAC shop. Neither is final, as far as we can confirm.

    1. Part 9A Boiler Code (new rule set)

    • LARA wants to “modernize and update” the boiler rules.
    • It would adopt the 2024 ASME Boiler and Pressure Vessel Code, ASME CSD-1 (controls and safety devices for automatically fired boilers) and the 2023 National Board Inspection Code.
    • It was published in the September 1, 2026 Michigan Register. The hearing was September 10, 2026, and comments closed Sept 11.
    • It takes effect 90 days after filing. As of Oct 15, 2026, the state has not filed it or published an effective date. Final rule text went to the Legislature’s rules committee Sept 29, 2026 (state rule tracker, 2025-64 LR).

    Who cares: shops that install, repair or service boilers. CSD-1 covers controls and safety devices on automatically fired boilers, which is right in a hydronic tech’s lane. The final text is posted on the state rule tracker. Check what changes for your work before it takes effect.

    2. Skilled Trades Regulation rules

    • This is the rule set behind licensing under the Skilled Trades Regulation Act.
    • LARA says it would set “clear and consistent fees and experience requirements” for registrations, licenses and exam applications. It also addresses continuing education, clarifies complaint procedures, and moves the boiler rules out into the new Boiler Code rule set.
    • Same timeline: Register Sept 1, hearing Sept 10, 2026, effective 90 days after filing. As of Oct 15, 2026, not filed and no effective date (state rule tracker, 2025-58 LR).

    Who cares: anyone holding or hiring for a Michigan trades license. Fees or experience rules for new applicants could change. The final text is on the state rule tracker. It isn’t in effect yet, so today’s fees and CE rules still apply.

    Example

    You’re about to sponsor a tech for a mechanical contractor exam in spring 2027. If these rules are filed this winter, the application fee or experience paperwork might be different by then. Check LARA’s page before you submit.

    What to do

    • Subscribe to LARA notices: email LARA-BCC-Rules@michigan.gov with the rule set name in the subject.
    • We’ll report the final text when it’s filed.

    Source: LARA BCC currently open rules

    More for HVAC/Mechanical contractors: Michigan HVAC/Mechanical updates.

    Michigan Code Brief · Not legal advice. Every fact links to its official source. Checked Oct 15, 2026. Confirm with LARA or your local building department before you act.

  • R-410A: the federal install deadline is gone

    For two years we heard “you can’t install R-410A after January 1, 2026.” That’s no longer true. EPA removed the deadline.

    What happened

    • EPA’s 2023 Technology Transitions rule set a GWP limit of 700 for new residential and light-commercial AC and heat pump systems. R-410A is well above 700. R-454B and R-32 are under it.
    • New systems like that couldn’t be made or imported after January 1, 2025.
    • A December 2023 interim rule let contractors install leftover inventory through December 31, 2025, if every component was made or imported before Jan 1, 2025.
    • In 2026 EPA finalized a reconsideration rule (published in the Federal Register May 26, 2026, 91 FR 31284). It took effect July 27, 2026 and removed the installation deadline for those qualifying systems.

    What it means for you

    • You can install an R-410A split system, mini-split or packaged unit for residential or light commercial with no federal end date, as long as every specified component was manufactured or imported before January 1, 2025.
    • New R-410A systems still can’t be manufactured or imported. Supply only shrinks from here.
    • Servicing existing R-410A systems is still allowed. EPA kept the ability to use replacement components labeled “for servicing existing equipment only.”

    Practical example

    A customer’s 2012 R-410A heat pump dies. They want the cheapest replacement. Your distributor has a matched R-410A condenser and coil. Check the manufacture date on both. Both pre-2025? Federally, you’re fine. One made after Jan 1, 2025? Don’t install that combo. Keep a photo of the data plates in the job file.

    Don’t over-read it

    This is the federal rule. Michigan’s construction code applies statewide (MCL 125.1508a), and the current Michigan Mechanical Code rules don’t mention R-410A or HFC phase-down dates (Part 9A rules). For A2L refrigerants (R-454B, R-32), the Michigan Mechanical Code says A2L systems “shall comply with ASHRAE 15” (R 408.30947b). Follow the manufacturer’s instructions too.

    What to do

    • Ask your distributor for date codes before you quote R-410A.
    • Keep training techs on A2L equipment. That’s where new product is going.

    Sources: Federal Register, 91 FR 31284 · EPA restrictions by sector · ABC summary

    More for HVAC/Mechanical contractors: Michigan HVAC/Mechanical updates.

    Michigan Code Brief · Not legal advice. Every fact links to its official source. Checked Oct 15, 2026. Confirm with LARA or your local building department before you act.